Skip to main content
Qipu

Public contracts of Lignéville · 2023

Amélioration du réseau d’eau potable tranche 2

The largest contract Lignéville awarded in 2023, out of 2.

Contract · Energy · carried out in 88800

121k €
contract ceiling — what was paid on it is not published
Signed on 25 September 2023 · ended around April 2024 · 0.6 yrs
Ended25 Apr 2024

Who won it

Société Travaux Publics et IndustrielsSIREN 332803345

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 2 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceFerme
Published amendmentsnone

Other contracts of Société Travaux Publics et Industriels in Lignéville

Réseau eau tranche 2 phase 2202460k€Création défense incendie202355k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method