Public contracts of Louviers · 2024 · Construction and buildings

Construction d’un complexe sportif au stade Carrington : gros œuvre et maçonnerie

€1M
maximum contract amount over 15 months — what was paid on it is not published
Signed on 13 May 2024 · ended around August 2025 · 15 months

That is at most ~€822k a year on average: a maximum too.

Company selected

Entreprise BouquetTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Vernon (27200) · headcount 20 to 49 employees · SIREN 573650728

The competition

7 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 26 contracts Louviers published for 2024.

Other contracts of Entreprise Bouquet in Louviers

École primaire des Acacias et accueil de loisirs : terrassements…2025 · maximum over 19 months1.5€MReconstruction de la crèche des Acacias : fondations profondes et gros…2023 · maximum over 15 months283€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 12

Subcontracting declared : yes