Skip to main content

Public contracts of Lunéville · 2021 · Construction and buildings

Consolidation et aménagement du gymnase de la Barollière : gros œuvre et charpente

€215k
maximum contract amount over 8 months — what was paid on it is not published
Signed on 19 May 2021 · ended around January 2022 · 8 months

Company selected

Adami ConstructionTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Luneville (54300) · headcount 20 to 49 employees · SIREN 783273915

Number 6 by amount of the 28 contracts Lunéville published for 2021. It belongs to the policy Culture, sport and youth.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.