Public contracts of Lurcy-Lévis · 2022 · Construction and buildings

Construction d’une maison de santé pluridisciplinaire : plâtrerie et peinture

€180k
maximum contract amount over 13 months — what was paid on it is not published
Signed on 4 July 2022 · ended around August 2023 · 13 months

That is at most ~€166k a year on average: a maximum too.

Company selected

Entreprise BongletTravaux de plâtrerie · registered office Lons-Le-Saunier (39000) · headcount 500 to 999 employees · SIREN 315434852

Number 3 by amount of the 10 contracts Lurcy-Lévis published for 2022.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.