Public contracts of Lyon · 2019 · Energy

Fourniture d’électricité pour la ville et le CCAS (segments C3 et C4)

€14.1M
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 30 July 2019 · ended around July 2023 · 4 yrs

That is at most ~€3.5M a year on average: a maximum too.

Company selected

Geg Source d'ÉnergiesCommerce d'électricité · registered office Grenoble (38000) · SIREN 321213225

A contract awarded to 4 holders; above, the main holder. With it: Enalp, Engie, Électricité de France (Dir Commerciale GRDS Clients). The amount is the whole contract’s: the DECP does not publish each holder’s share.

The largest of the 385 contracts Lyon published for 2019.

Other contracts of Geg Source d'Énergies in Lyon

Fourniture d’électricité pour la ville et le CCAS2019 · maximum over 4 years10€MFourniture et acheminement d’électricité pour la ville et le CCAS…2019 · maximum over 3 years4.7€M
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.