Public contracts of Lyon · 2026 · Construction and buildings

Médiathèque marceline desbordes valmore

Réaménagement intérieur · Électricité

€260k
maximum contract amount over 14 months — what was paid on it is not published
Signed on 19 May 2026 · running until about July 2027 · 14 months
Ongoing19 Jul 2027

That is at most ~€223k a year on average: a maximum too.

Company selected

Reverchon ÉlectricitéTravaux d'installation électrique dans tous locaux · registered office Saint-Fons (69190) · headcount 20 to 49 employees · SIREN 481632347

Number 197 by amount of the 542 contracts Lyon published for 2026.

Other contracts of Reverchon Électricité in Lyon

Mairie du 9e arrondissement2026 · maximum over 15 months285€kVilla Gillet2026 · maximum over 18 months245€kMaison de l’Enfance et de la Jeunesse de la Croix-Rousse2026 · maximum over 11 months229€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Social considerations : Clause sociale

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.