Skip to main content

Public contracts of M'Tsangamouji · 2022 · Construction and buildings

Rénovation école maternelle centre

€434k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 1 December 2022 · ended around January 2023 · 2 months

Company selected

AlbertTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Chirongui (97620) · SIREN 501900989

Number 7 by amount of the 34 contracts M'Tsangamouji published for 2022. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : 2

The 2 lots : 249 €k · 185 €k

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.