Skip to main content

Public contracts of Mareil-Marly · 2022 · Construction and buildings

Travaux de signalisation horizontale

€80k
contract ceiling — what was paid on it is not published
Signed on 4 July 2022 · ended around July 2026 · 4 yrs

Who won it

AximumConstruction de routes et autoroutes · registered office Magny-Les-Hameaux (78114) · headcount 1,000 to 1,999 employees · SIREN 582081782

Number 24 by amount of the 25 contracts Mareil-Marly published for 2022.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.