Public contracts of Margny-lès-Compiègne · 2024 · Construction and buildings

Travaux de réfection de toiture et d’isolation des écoles élémentaires Edouard Herriot et Paul Bert à Margny-lès-Compiègne

École élémentaire Paul Bert

€51k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 19 April 2024 · ended around June 2024 · 2 months

Company selected

—SIREN 809745059

Number 4 by amount of the 4 contracts Margny-lès-Compiègne published for 2024. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.