Skip to main content

Public contracts of Maripasoula · 2024 · Construction and buildings

Extension du réseau d’eau potable du bourg de Maripasoula

€270k
maximum contract amount over 3 months — what was paid on it is not published
Signed on 10 April 2024 · ended around July 2024 · 3 months

Company selected

Sogea GuyaneConstruction de réseaux pour fluides · registered office Remire-Montjoly (97354) · headcount 100 to 199 employees · SIREN 352411706

The competition

2 bids received

Median for this procedure in 2024: 3 bids, across 48741 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 8 by amount of the 18 contracts Maripasoula published for 2024.

Other contracts of Sogea Guyane in Maripasoula

Construction du plateau sportif Taluhen2025 · maximum over 12 months644€kExtension du réseau de collecte des eaux usées, tranche 5F-6C2024 · maximum over 8 months5.8€MTravaux création des réseaux AEP de la piste agricole2021 · maximum over 2 months96€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.