Public contracts of Méry-sur-Marne · 2025 · Construction and buildings

Extension de la salle polyvalente

€724k
maximum contract amount over 8 months — what was paid on it is not published
Signed on 17 November 2025 · ended around July 2026 · 8 months

Company selected

Entreprise de Construction PortierConstruction d'autres bâtiments · registered office Fontenay-Sous-Bois (94120) · headcount 20 to 49 employees · SIREN 304864093

A contract awarded to 2 holders; above, the main holder. With it: SAS Top Aménagement. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

4 bids received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 2 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 2 contracts Méry-sur-Marne published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 2

Subcontracting declared : yes

The 2 lots : 444 €k · 280 €k

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.