Skip to main content

Public contracts of Meslay-du-Maine · 2025 · Construction and buildings

Maîtrise d’oeuvre pour la création d’un nouveau quartier

€63k
maximum contract amount over 14 months — what was paid on it is not published
Signed on 21 July 2025 · ended around September 2026 · 14 months

That is at most ~€54k a year on average: a maximum too.

Who won it

Sitadin - Urbanisme et PaysageIngénierie, études techniques · registered office Rennes (35000) · headcount 3 to 5 employees · SIREN 449835958

A contract awarded to a consortium of 3 holders; above, the main holder. With it: Plaine Etude, Iao Senn. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

6 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 3 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 6 by amount of the 6 contracts Meslay-du-Maine published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.