Public contracts of Metz · 2024 · Construction and buildings

Centre victor desvignes déconstruction bâtiment

€85k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 15 November 2024 · ended around June 2025 · 7 months

Company selected

Entreprise HollingerTravaux de démolition · registered office Pont-A-Mousson (54700) · headcount 20 to 49 employees · SIREN 493531271

The competition

8 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 326 by amount of the 513 contracts Metz published for 2024.

Other contracts of Entreprise Hollinger in Metz

Ms0 bdc-3e attributaire2024 · maximum over 3 years833€kTravaux de déconstruction et de démolition de la médiathèque de Borny2024 · maximum over 8 months138€kLot no1 démolition2024 · maximum over 9 months89€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : 6

Social considerations : Clause sociale

Environmental considerations : Clause environnementale