Skip to main content

Public contracts of Metz · 2022 · Construction and buildings

Ascenseur-centre social de Borny

€51k
maximum contract amount over 2.5 years — what was paid on it is not published
Signed on 16 June 2022 · ended around October 2024 · 2.5 yrs

That is at most ~€22k a year on average: a maximum too.

Company selected

Orona EstAutres travaux d'installation n.c.a. · registered office Strasbourg (67200) · headcount 20 to 49 employees · SIREN 338508120

A contract awarded to 2 holders; above, the main holder. With it: Orona. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 263 by amount of the 352 contracts Metz published for 2022.

Other contracts of Orona Est in Metz

Construction d’un centre social à Borny2022 · maximum over 20 months51€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Mixte

Published amendments : 11

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.