Public contracts of Metz · 2023 · Construction and buildings

RPLT éclairage public quartier magny phase 2

€227k
maximum contract amount over 13 months — what was paid on it is not published
Signed on 10 July 2023 · ended around August 2024 · 13 months

That is at most ~€209k a year on average: a maximum too.

Company selected

Travaux Souterrains Electriques et Gaziers (Citeos)Travaux d'installation électrique sur la voie publique · registered office Basse-Ham (57970) · headcount 20 to 49 employees · SIREN 421535683

A contract awarded to 2 holders; above, the main holder. With it: Sdel Lumiere (Citeos). The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 53 by amount of the 224 contracts Metz published for 2023.

Other contracts of Travaux Souterrains Electriques et Gaziers (Citeos) in Metz

A bdc-3e ATT-Travaux neufs rénovation éclairage2024 · maximum over 3 years1.8€MHorloges connectées2023 · maximum over 13 months367€kRPLT éclairage public quartiers devant les ponts patrotte Metz nord…2023 · maximum over 4 months275€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : 5

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.