Public contracts of Mionnay · 2026
construction d’une salle de sports - charpente bois
The largest contract Mionnay awarded in 2026, out of 6.
Original label (DECP) : « construction d’une salle de sports - charpente bois » · Contract · Construction and Bâtiment · Travaux · carried out in 01
336k €
contract ceiling — what was paid on it is not published
Who won it
Favrat Construction BoisSIREN 797080322The competition
77 bids received
Adapted procedure · awarded to 1 company
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
The form of the contract
PriceForfaitaire
Published amendments2
Subcontracting declaredyes
Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.