Public contracts of Moncé-en-Belin · 2023 · Energy

Marché électricité jaune

CSC, Stade, Salle de sport du 01/01/2024 au 31/12/2027 et Groupe Scolaire du 01/01/2026 au 31/12/2027

€128k
maximum contract amount over 4 years — what was paid on it is not published
Signed on 12 September 2023 · running until about September 2027 · 4 yrs
Ongoing12 Sept 2027

That is at most ~€32k a year on average: a maximum too.

Who won it

Primeo Énergie FranceCommerce d'électricité · registered office Paris (75009) · headcount 50 to 99 employees · SIREN 808283345

What was actually paid

Electricity, gas and heating: €116k paid by Moncé-en-Belin in 2023, all suppliers together (its accounts). The accounts do not say what share went to Primeo Énergie France.

Number 2 by amount of the 5 contracts Moncé-en-Belin published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.