Public contracts of Mondoubleau · 2024 · Construction and buildings

Marché maîtrise d’œuvre Restauration des toitures de la Nef et de la Chapelle sud de l’Église Saint-Denis

€62k
maximum contract amount over 10 months — what was paid on it is not published
Signed on 20 September 2024 · ended around July 2025 · 10 months

Who won it

EcpActivité des économistes de la construction · registered office Blois (41000) · headcount 1 or 2 employees · SIREN 799347547

A contract awarded to 2 holders; above, the main holder. With it: Pereira Architectes. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 2 by amount of the 2 contracts Mondoubleau published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.