Mise en oeuvre d’un rideau de palplanches Berges du Midou

€92k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 15 July 2021 · ended around February 2022 · 7 months

Company selected

Roy TravauxTravaux de terrassement courants et travaux préparatoires · registered office Pouydesseaux (40120) · headcount 50 to 99 employees · SIREN 414503565

Number 37 by amount of the 58 contracts Mont-de-Marsan published for 2021.

Other contracts of Roy Travaux in Mont-de-Marsan

Agrandissement et modernisation du musée Despiau Wlérick de…2026 · maximum over 3.5 years109€kTerrassement2026 · maximum over 3 years109€kVoirie et réseaux divers2024 · maximum over 12 months81€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : 2

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.