Public contracts of Mont Lozère et Goulet · 2025 · Construction and buildings

Travaux pour la Réhabilitation de l’école primaire du Bleymard

Plafonds démontables

€13k
maximum contract amount over 11 months — what was paid on it is not published
Signed on 10 October 2025 · ended around September 2026 · 11 months

Who won it

Société Nouvelle Entreprise BoulardAutres travaux de finition · registered office Chastel-Nouvel (48000) · headcount 3 to 5 employees · SIREN 513270272

The competition

2 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 39 by amount of the 46 contracts Mont Lozère et Goulet published for 2025.

Other contracts of Société Nouvelle Entreprise Boulard in Mont Lozère et Goulet

Réhabilitation de l’ancienne boulangerie en mairie et salle hors sac…2025 · maximum over 23 months6€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.