Public contracts of Montaigu-le-Blin · 2025 · Construction and buildings

Déconstruction, maçonnerie et gros œuvre

€127k
maximum contract amount over 8 months — what was paid on it is not published
Signed on 1 April 2025 · ended around December 2025 · 8 months

Company selected

SAS Sabot J.L. et Fils (SARL Sabot Jean-Luc)Travaux de maçonnerie générale et gros œuvre de bâtiment · registered office Paray-Sous-Briailles (03500) · headcount 10 to 19 employees · SIREN 391746732

Number 3 by amount of the 10 contracts Montaigu-le-Blin published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.