Skip to main content

Public contracts of Montélimar · 2026 · Construction and buildings

Divers travaux de bâtiments

Carrelage, faïence, revêtement de sols

€350k
contract ceiling — what was paid on it is not published
Signed on 17 August 2026 · running until about August 2028 · 2 yrs
Ongoing17 Aug 2028

Who won it

CHM EntretienTravaux de revêtement des sols et des murs · registered office Fontaine (38600) · headcount 20 to 49 employees · SIREN 825398043

A contract awarded to 2 holders; above, the main holder. With it: SAS Rigoudy. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

2 bids received

Median for this procedure in 2026: 3 bids, across 20741 comparable contracts. Simplified procedure · awarded to 2 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 10 by amount of the 48 contracts Montélimar published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.