Skip to main content
Qipu

Public contracts of Montereau-Fault-Yonne · 2022

Réalisation de travaux de climatisation dans deux écoles maternelles de la Ville de Montereau-Fault-Yonne - Travaux de climatisation de l’école maternelle BOYER

Number 19 by amount of the 43 contracts Montereau-Fault-Yonne awarded in 2022.

Original label (DECP) : « Réalisation de travaux de climatisation dans deux écoles maternelles de la Ville de Montereau-Fault-Yonne - Travaux de climatisation de l’école maternelle BOYER » · Contract · Construction and Bâtiment · Travaux · carried out in 77

123k €
contract ceiling — what was paid on it is not published
Signed on 16 June 2022 · ended around August 2022 · 0.2 yrs
Ended16 Aug 2022

Who won it

SoclmSIREN 522174200

The competition

12 bids received

awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceForfaitaire
Published amendmentsnone
Subcontracting declaredno

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method