Skip to main content

Public contracts of Monteux · 2025 · Construction and buildings

Travaux de réfection structurelle d’une coursive en béton au Château d’Eau

Gros oeuvre

€91k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 26 February 2025 · ended around September 2025 · 7 months

Company selected

Bratis Construction (Maconnerie Générale)Travaux de maçonnerie générale et gros œuvre de bâtiment · registered office Vedene (84270) · SIREN 444501746

The competition

6 bids received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 10 by amount of the 25 contracts Monteux published for 2025.

Other contracts of Bratis Construction (Maconnerie Générale) in Monteux

Réfection structurelle de la coursive en béton armé longeant la salle…2025 · maximum over 7 months89€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 4

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.