Public contracts of Montfrin · 2024 · Construction and buildings
Construction d’un groupe scolaire de 13 classes regroupant les écoles maternelle, élémentaire et le centre de loisirs
Revetements de SOL · Faiences
That is at most ~€156k a year on average: a maximum too.
Company selected
SARL CuberoTravaux de plâtrerie · registered office Baillargues (34670) · headcount 6 to 9 employees · SIREN 499308252A contract awarded to a consortium of 2 holders; above, the main holder. With it: Tech SOL. The amount is the whole contract’s: the DECP does not publish each holder’s share.
The competition
Median for this procedure in 2024: 3 bids, across 17972 comparable contracts. Open tender · awarded to 2 companies
Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.
Number 18 by amount of the 44 contracts Montfrin published for 2024.
Other contracts of SARL Cubero in Montfrin
Construction d’un groupe scolaire : revêtements de sol et faïences2024 · maximum over 16 months225€kContract details (procedure, price, amendments, lots)
Procedure : Appel d'offres ouvert
Price : Forfaitaire
Published amendments : none
Subcontracting declared : no
Social considerations : Clause sociale
Environmental considerations : Critère environnemental
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.