Public contracts of Montfrin · 2024 · Construction and buildings

Construction d’un groupe scolaire de 13 classes regroupant les écoles maternelle, élémentaire et le centre de loisirs

Photovoltaique

€42k
maximum contract amount over 16 months — what was paid on it is not published
Signed on 6 September 2024 · ended around January 2026 · 16 months

That is at most ~€32k a year on average: a maximum too.

Company selected

Entreprise MarcTravaux d'installation électrique dans tous locaux · registered office Villeneuve-Les-Beziers (34500) · headcount 100 to 199 employees · SIREN 632920740

The competition

7 bids received

Median for this procedure in 2024: 3 bids, across 17972 comparable contracts. Open tender · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 38 by amount of the 44 contracts Montfrin published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Environmental considerations : Critère environnemental