Conception, construction et exploitation-maintenance d’un centre social

€3.2M
maximum contract amount over 12.5 years — what was paid on it is not published
Signed on 26 December 2024 · running until about March 2037 · 12.5 yrs
Ongoing28 Mar 2037

That is at most ~€263k a year on average: a maximum too.

Company selected

Ramery ÉnergiesTravaux d'installation d'équipements thermiques et de climatisation · registered office Erquinghem-Lys (59193) · headcount 250 to 499 employees · SIREN 356200295

A contract awarded to a consortium of 5 holders; above, the main holder. With it: Etnap BET, SARL Solener, Ramery Construction, Scenario-ARA. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

2 bids received

Median for this procedure in 2024: 3 bids, across 740 comparable contracts. Procedure with negotiation · awarded to 5 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 21 contracts Montigny-en-Gohelle published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Procédure avec négociation

Price : Mixte

Published amendments : 27

Subcontracting declared : yes