Rénovation du bâtiment des Hallettes à Montivilliers

€12k
maximum contract amount over 5 months — what was paid on it is not published
Signed on 17 July 2019 · ended around December 2019 · 5 months

Company selected

Peinture Bâtiment IndustrieTravaux de peinture et vitrerie · registered office Gonfreville-L'Orcher (76700) · headcount 20 to 49 employees · SIREN 334850757

Number 54 by amount of the 69 contracts Montivilliers published for 2019.

Other contracts of Peinture Bâtiment Industrie in Montivilliers

Aménagement des locaux de la cité administrative de Montivilliers…2019 · maximum over 6 months27€kTravaux de remise en état du gymnase Jean Prévost suite à un incendie2019 · maximum over 3 months14€kTraitement des charpentes bois de l’hôtel de ville…2019 · maximum over 2 months5€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.