Public contracts of Montpellier · 2024 · Construction and buildings
Construction crèche Mireille Laget
Électricité courants forts et courants faibles
That is at most ~€97k a year on average: a maximum too.
Company selected
Tec Elec SudTravaux d'installation électrique dans tous locaux · registered office Saint-Martin-De-Londres (34380) · headcount 10 to 19 employees · SIREN 822386991The competition
Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company
Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.
Number 154 by amount of the 266 contracts Montpellier published for 2024. It belongs to the policy Health and social care.
Other contracts of Tec Elec Sud in Montpellier
Construction du groupe scolaire croix d’argent de 17 classes2025 · maximum over 2.5 years540€kConstruction du groupe scolaire croix d’argent de 17 classes2025 · maximum over 2.5 years144€kÉlectricité courants forts et faibles2024 · maximum over 18 months145€kContract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Price : Forfaitaire
Published amendments : none
Subcontracting declared : no
Social considerations : Clause sociale
Environmental considerations : Clause environnementale
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.