Public contracts of Montrevault-sur-Èvre · 2026 · Construction and buildings

Location d’un bâtiment modulaire pour l’école publique de chaudron-en-mauges

€129k
maximum contract amount over 17 months — what was paid on it is not published
Signed on 21 May 2026 · running until about October 2027 · 17 months
Ongoing20 Oct 2027

That is at most ~€91k a year on average: a maximum too.

Company selected

CougnaudFabrication de structures métalliques et de parties de structures · registered office Mouilleron-Le-Captif (85000) · headcount 1,000 to 1,999 employees · SIREN 892298324

The competition

4 bids received

Median for this procedure in 2026: 3 bids, across 23502 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 20 by amount of the 50 contracts Montrevault-sur-Èvre published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : none

Subcontracting declared : no

The 2 lots : 117 €k · 12 €k

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.