Rénovation CET

Électricité

€42k
maximum contract amount over 8 months — what was paid on it is not published
Signed on 23 February 2024 · ended around October 2024 · 8 months

Company selected

MeloniTravaux d'installation électrique dans tous locaux · registered office Saint-Avold (57500) · headcount 10 to 19 employees · SIREN 813880937

The competition

2 bids received

Median for this procedure in 2024: 3 bids, across 48741 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 17 by amount of the 23 contracts Morsbach published for 2024.

Other contracts of Meloni in Morsbach

Travaux pour la rénovation du centre Eric Tabarly à Morsbach2024 · maximum over 8 months35€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Social considerations : Clause sociale