Public contracts of Muzillac · 2022 · Construction and buildings

Rénovation du centre d’animation du Vieux Couvent : électricité

€374k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 16 April 2022 · ended around October 2023 · 18 months

That is at most ~€250k a year on average: a maximum too.

Company selected

DC ÉnergieTravaux d'installation électrique dans tous locaux · registered office Muzillac (56190) · headcount 20 to 49 employees · SIREN 324477942

Number 8 by amount of the 50 contracts Muzillac published for 2022.

Other contracts of DC Énergie in Muzillac

Salle de spectacle, école de musique et salles de réunion…2022 · maximum over 18 months374€kExtension de la maison de l’enfance.14 lots2020 · maximum over 12 months93€kExtension de la maison de l’enfance.14 lots2020 · maximum over 12 months18€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : 6

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.