Public contracts of Neuville-en-Ferrain · 2024 · Construction and buildings

Requalification de la ferme du Vert Bois : gros œuvre

La ferme du Vert Bois est requalifiée. Ce lot 1 réalise le gros œuvre, c'est-à-dire la structure du bâtiment : fondations, murs porteurs et planchers.

€1.5M
maximum contract amount over 20 months — what was paid on it is not published
Signed on 13 December 2024 · ended around August 2026 · 20 months

That is at most ~€871k a year on average: a maximum too.

Company selected

Helfaut TravauxTravaux de démolition · registered office Helfaut (62570) · headcount 50 to 99 employees · SIREN 318290988

A contract awarded to a consortium of 2 holders; above, the main holder. With it: Rabot Dutilleul Construction. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

4 bids received

Median for this procedure in 2024: 3 bids, across 17968 comparable contracts. Open tender · awarded to 2 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 5 contracts Neuville-en-Ferrain published for 2024. It belongs to the policy Town planning and housing.

Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Forfaitaire

Published amendments : 5

Subcontracting declared : yes

Social considerations : Clause sociale

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.