DPM 2019-22-Gros œuvre

Travaux de réaménagement du groupe scolaire Jacques Prévert à Niort

€144k
maximum contract amount over 14 months — what was paid on it is not published
Signed on 18 June 2019 · ended around August 2020 · 14 months

That is at most ~€123k a year on average: a maximum too.

Company selected

Troubat SATravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Niort (79000) · SIREN 305060691

Number 48 by amount of the 118 contracts Niort published for 2019. It belongs to the policy Schools.

Other contracts of Troubat SA in Niort

Travaux de rénovation des façades groupe scolaire Jules Ferry2019 · maximum over 4 months126€kDPM 2019-22-Démolition2019 · maximum over 14 months44€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.