Public contracts of Niort · 2019 · Construction and buildings

DPM 2019-26-Charpente bois

Construction de vestiaires au stade de Cholette

€9k
maximum contract amount over 11 months — what was paid on it is not published
Signed on 4 July 2019 · ended around June 2020 · 11 months

Company selected

Charpente Menuiserie Billy SATravaux de charpente · registered office Bressuire (79300) · headcount 20 to 49 employees · SIREN 339705295

Number 117 by amount of the 118 contracts Niort published for 2019. It belongs to the policy Culture, sport and youth.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.