Public contracts of Niort · 2021 · Construction and buildings

Gs sand Elem rénovation énergétique

Revêtements de sols scellés sols collés faïence

€88k
maximum contract amount over 3 years — what was paid on it is not published
Signed on 9 December 2021 · ended around December 2024 · 3 yrs

That is at most ~€29k a year on average: a maximum too.

Company selected

Batisol PlusTravaux de revêtement des sols et des murs · registered office Chatellerault (86100) · headcount 50 to 99 employees · SIREN 493461248

Number 68 by amount of the 120 contracts Niort published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : 2

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.