Création d’un bassin de rétention et d’un réseau d’eaux pluviales boulevard charbonneau et rouxeau

€70k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 26 August 2019 · ended around February 2021 · 18 months

That is at most ~€46k a year on average: a maximum too.

Company selected

Guilloteau TPTravaux de terrassement courants et travaux préparatoires · registered office Loireauxence (44370) · headcount 10 to 19 employees · SIREN 441004744

Number 6 by amount of the 15 contracts Nort-sur-Erdre published for 2019.

Other contracts of Guilloteau TP in Nort-sur-Erdre

Programme d’aménagement de la voirie communale 20192019 · maximum over 1 month87€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.