Skip to main content

Public contracts of Nort-sur-Erdre · 2023 · Professional services

Maîtrise d’oeuvre complète + ordonnancement, pilotage et coordination pour la requalification des terrains du stade municipal

€19k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 9 February 2023 · ended around February 2024 · 12 months

Company selected

Atelier Chaneac ArchitectureActivités d'architecture · registered office Challes-Les-Eaux (73190) · headcount 3 to 5 employees · SIREN 393269808

Number 27 by amount of the 44 contracts Nort-sur-Erdre published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.