Public contracts of Noues de Sienne · 2024 · Construction and buildings

Pôle petite enfance

Chauffage Ventilation Plomberie

€109k
maximum contract amount over 14 months — what was paid on it is not published
Signed on 2 April 2024 · ended around June 2025 · 14 months

That is at most ~€93k a year on average: a maximum too.

Company selected

Lemonnier BâtimentTravaux d'installation d'eau et de gaz en tous locaux · registered office Gavray-Sur-Sienne (50450) · headcount 20 to 49 employees · SIREN 821774536

A contract awarded to 2 holders; above, the main holder. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

5 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 2 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 9 by amount of the 24 contracts Noues de Sienne published for 2024.

Other contracts of Lemonnier Bâtiment in Noues de Sienne

Construction d’un pôle petite enfance2024 · maximum over 14 months109€kConstruction d’un pôle petite enfance2024 · maximum over 14 months38€kRéhabilitation de l’ancienne salle des fêtes en salle associative…2021 · maximum over 8 months64€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire