Skip to main content
Qipu

Public contracts of Nozay · 2019

Nouvel Accord Cadre à BDC

Accord-cadre · Construction and Bâtiment · carried out in 44170

208k €
contract ceiling — what was paid on it is not published
Signed on 27 August 2019 · ended around August 2020 · 1.0 yrs
Ended26 Aug 2020

Who won it

Charier TP (Charier Routes & Travaux Urbains Nozay)SIREN 343691374

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

Framework agreementyes: orders follow, the amount is a ceiling
PriceRévisable
Published amendmentsnone

Other contracts of Charier TP (Charier Routes & Travaux Urbains Nozay) in Nozay

Aménagement secteur de jouvence2026330k€Travaux de voirie et réseaux20241.2M€Nouveau Marché Ordinaire2023219k€AGT voirie rte rennes et secteur de la base de loisirs2022814k€Aménagement rues ère nouvelle et victor hugo2022239k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method