Skip to main content

Public contracts of Obernai · 2019 · Construction and buildings

Travaux de restauration et de mise en valeur de l’église Saints Pierre-et-Paul

Vitrail

€80k
maximum contract amount over 20 months — what was paid on it is not published
Signed on 13 August 2019 · ended around April 2021 · 20 months

That is at most ~€48k a year on average: a maximum too.

Company selected

Atelier Art VitrailFabrication et façonnage d'autres articles en verre, y compris verre technique · registered office Gurgy (89250) · headcount 10 to 19 employees · SIREN 822676839

Number 20 by amount of the 33 contracts Obernai published for 2019. It belongs to the policy Culture, sport and youth.

Other contracts of Atelier Art Vitrail in Obernai

Restauration de la rosace de l’Église Saints-Pierre-et-Paul (2021 · maximum over 4 months46€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.