Public contracts of Ondres · 2023 · Construction and buildings

Gros œuvre

€90k
contract ceiling — what was paid on it is not published
Signed on 15 March 2023 · ended around March 2026 · 3 yrs

Who won it

E.L.M. ConstructionTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Hasparren (64240) · headcount 10 to 19 employees · SIREN 753486166

Number 14 by amount of the 18 contracts Ondres published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Gros œuvre: €90k, Ondres 2023 · Qipu