Rénovation des peintures intérieures et extérieures et des sols des bâtiments communaux

€800k
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 17 December 2019 · ended around December 2023 · 4 yrs

That is at most ~€200k a year on average: a maximum too.

Company selected

Berin PlafondsConstruction de maisons individuelles · registered office Sivry-Courtry (77115) · headcount 6 to 9 employees · SIREN 407728013

Number 3 by amount of the 56 contracts Orsay published for 2019. It belongs to the policy Administration and shared services.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.