Public contracts of Passy · 2024 · Construction and buildings

Construction de l’école de musique et de danse : menuiseries intérieures

€532k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 3 September 2024 · ended around March 2026 · 18 months

That is at most ~€355k a year on average: a maximum too.

Company selected

Menuiserie Pellet- JambazTravaux de menuiserie bois et PVC · registered office Boege (74420) · headcount 10 to 19 employees · SIREN 479560039

The competition

4 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 4 by amount of the 67 contracts Passy published for 2024. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 3

Social considerations : Clause sociale

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.