Skip to main content

Public contracts of Péone · 2022 · Construction and buildings

Gros œuvre, démolition, sols durs, faïences et étanchéité

€243k
maximum contract amount over 1 month — what was paid on it is not published
Signed on 23 March 2022 · ended around April 2022 · 1 month

Company selected

Société de Coordination et Realisation de TravauxTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office La Gaude (06610) · headcount 6 to 9 employees · SIREN 507759827

Number 6 by amount of the 18 contracts Péone published for 2022.

Other contracts of Société de Coordination et Realisation de Travaux in Péone

Travaux au chalet de Péri2026 · maximum over 12 months369€kPeomapa2026-12-tranche unique2026 · maximum over 6 months190€kPeopspnmcp2026-42026 · maximum over 6 months137€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.