Skip to main content

Public contracts of Péronne-en-Mélantois · 2021 · Construction and buildings

Extension de la cantine scolaire

Ce02 Etanchéité

€41k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 9 December 2021 · ended around December 2022 · 12 months

Company selected

Métropole ConstructionTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Roubaix (59100) · headcount 20 to 49 employees · SIREN 439619776

Number 12 by amount of the 12 contracts Péronne-en-Mélantois published for 2021.

Other contracts of Métropole Construction in Péronne-en-Mélantois

Extension de la cantine scolaire : démolition, gros œuvre, voirie…2021 · maximum over 12 months211€kConstruction de la salle multiculturelle2021 · maximum over 11 months145€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.