Construction de la nouvelle station d epuration du Bourg de Pierre-de-Bresse

The largest contract Pierre-de-Bresse awarded in 2025, out of 2.

Contract · Construction and Bâtiment · Travaux · carried out in 71270

2.4€M
contract ceiling — what was paid on it is not published
Signed on 6 February 2025 · running until about October 2026 · 1.7 yrs
Ongoing8 Oct 2026

Who won it

HydreaSIREN 389074261

The competition

2 bids received

Adapted procedure · awarded to 3 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceUnitaire
Published amendments1
Subcontracting declaredyes

Other contracts of Hydrea in Pierre-de-Bresse

Construction d’une nouvelle station d’épuration du bourg d’une capacité de 2400EH, création d’un collecteur de rejet, raccordement sur le futur réseau d’eaux usées, déconstruction de la station…20242.4M€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method
Construction de la nouvelle station d epuration du Bourg de…: 2.4 M€, Pierre-de-Bresse 2025 · Qipu