Skip to main content
Qipu

Public contracts of Pinols · 2020

Réservoir du bourg étanchéification et rénovation de la chambre des vannes

Contract · Construction and Bâtiment · carried out in 43300

48k €
contract ceiling — what was paid on it is not published
Signed on 23 July 2020 · ended around September 2020 · 0.2 yrs
Ended22 Sept 2020

Who won it

Gaillard ConstructionsSIREN 328356985

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceFerme et actualisable
Published amendmentsnone

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method