Skip to main content

Public contracts of Plabennec · 2023 · Construction and buildings

Extension de l’école maternelle : gros œuvre

€166k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 1 March 2023 · ended around May 2024 · 15 months

That is at most ~€133k a year on average: a maximum too.

Company selected

SAS Albert Larvor et CieTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Brest (29200) · headcount 20 to 49 employees · SIREN 636020133

The largest of the 30 contracts Plabennec published for 2023. It belongs to the policy Schools.

Other contracts of SAS Albert Larvor et Cie in Plabennec

Extension et réhabilitation de l’école maternelle du Lac à Plabennec2023 · maximum over 10 months139€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.