Skip to main content

Public contracts of Poey-de-Lescar · 2022 · Construction and buildings

Désamiantage de charpente et couverture métallique

€303k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 15 July 2022 · ended around February 2023 · 7 months

Who won it

SARL Barthe et FilsFabrication de structures métalliques et de parties de structures · registered office Viodos-Abense-De-Bas (64130) · headcount 6 to 9 employees · SIREN 344785365

Number 2 by amount of the 5 contracts Poey-de-Lescar published for 2022.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.